Maintainer(s)
 1. Phil McCullough 
Open Issues
  Date Desc Priority
1.  06/19/19 Steps  Medium  
2.  06/19/19 Downed Tree(s)  Medium  
3.  06/19/19 Tread Work  Low  
4.  03/27/19 Silt Bars(Construction)  Medium  
5.  03/27/19 Silt Bars(Construction)  Medium  
6.  03/20/19 Silt Bars(Construction)  Medium  
 
 
 
Maint History 2017-19
  Date Crew Count Work Hrs Travel Hrs
1.  03/19/19« 2 4 0
2.  03/20/19« 1 6 0
3.  03/27/19« 1 6 5